All articles

The CounselIssue 007

The Project Is Delayed — But Who Bears the Cost? Allocating Responsibility for Delay in UAE Construction Disputes

Construction delay claims are rarely resolved by comparing the contractual completion date with the actual completion date. Extension of Time claims, concurrent delay, variations, delayed approvals, liquidated damages and expert delay analysis can fundamentally change how responsibility is allocated between the parties.

  • Construction Disputes UAE
  • Construction Delay UAE
  • Contractor Claims UAE
  • Developer Disputes UAE
  • Extension of Time UAE
  • EOT Claims
  • Concurrent Delay UAE
  • Critical Path Analysis
  • Liquidated Damages UAE
  • Construction Expert UAE
  • Engineering Expert UAE
  • Variation Claims UAE
  • FIDIC UAE
  • Construction Law UAE
27 August 20268 min readShare on LinkedIn

Why it matters

The project has passed its contractual completion date. The project owner seeks delay damages. The contractor claims an Extension of Time. The project records, however, show delayed approvals, variations, changes to the sequence of works and periods of contractor underperformance.

This is where many construction disputes become significantly more complex.

The fact that a project was completed late does not, by itself, establish that the contractor is responsible for the entire period of delay.

For project owners and developers, delay may mean postponed operation of an investment asset, delayed unit handovers, lost expected revenue, additional financing exposure and extended project costs.

For contractors, it may result in substantial delay damages, rejection of Extension of Time claims, prolonged site costs and liability for periods of delay that they contend were caused by events outside their control.

The central question is therefore not simply:

How late was the project?

It is:

Who caused each period of delay, what effect did that event actually have on completion, and what can the project records prove?

Business insight

Construction delay should not be treated as a single block of time.

A project may experience late site access, delayed drawings, pending material approvals, variations, late instructions, insufficient contractor resources and procurement delays at different stages of execution.

Some of these events may affect completion. Others may not.

A three-week delay in approving a material does not automatically produce a three-week Extension of Time. If the contractor could continue other works and the delayed activity was not critical to completion, the actual effect may be significantly different.

Conversely, a relatively short event affecting a critical activity may disrupt a sequence of dependent works and materially move the completion date.

This is why sophisticated delay analysis focuses not merely on the existence of a delay event, but on its actual impact on the project programme and the critical path.

In a construction delay dispute, it is not enough to prove that an event occurred. The decisive issue is whether you can prove what that event actually did to the completion date.

Practical considerations

The strongest delay case is rarely created after proceedings begin.

Developers, project owners and contractors should manage project records in a manner that allows the history of the project to be reconstructed if a dispute later arises.

This does not mean treating every project as anticipated litigation. It means ensuring that significant events affecting time and cost are properly recorded when they occur.

  • Review the contractual completion date and all approved extensions
  • Preserve the original Baseline Programme and all subsequent programme updates
  • Identify each material delay event separately rather than treating delay as one continuous period
  • Determine which activities were affected by each event
  • Analyse whether the affected activities were on the Critical Path
  • Review all Extension of Time notices and supporting submissions
  • Match variations and consultant instructions to their actual programme impact
  • Maintain drawing and material approval logs
  • Preserve daily, weekly and monthly progress records
  • Record contractor resource shortages and procurement delays contemporaneously
  • Document delayed decisions, approvals or access attributable to the project owner or consultant
  • Separate Time Claims from Cost Claims
  • Review contractual notice requirements before entitlement becomes disputed
  • Prepare a chronological delay matrix linking each event to the relevant document, responsible party and alleged time impact

Boardroom question

If your project entered a delay dispute tomorrow, could your records demonstrate not merely that an event occurred, but exactly when it occurred, which activity it affected, whether that activity was critical, who was responsible and how many days it actually moved the completion date?

More insights

The Counsel · Issue 009September 2026

He Said It on WhatsApp — But Is It a Legal Admission? Electronic Messages in UAE Commercial Disputes

WhatsApp messages and emails are no longer merely tools of commercial communication. They may become evidence of a debt, approval, instruction or agreement. Yet the fact that a communication constitutes electronic evidence does not, by itself, make it a legal admission or establish the fact in dispute. Its significance may depend on authenticity, attribution, context, the authority of the sender and its consistency with the wider commercial record.

Read article

September 2026

Expedited Enforcement in Personal Status Cases under UAE Law

UAE law provides specific exceptions to the general rule that judgments may not be compulsorily enforced while they remain subject to appeal. Article 215 of Federal Decree by Law No. (42) of 2022 Promulgating the Civil Procedure Code provides for expedited enforcement by operation of law in specified personal status matters, including maintenance, wages and related expenses, as well as judgments concerning the handing over, seeing, visiting or escorting of a child.

Read article

The Counsel · Issue 008September 2026

Beyond the Trademark: When Does Similarity in Commercial Identity Become a Legal Dispute?

Trademark disputes do not always begin with an identical name or copied logo. The more difficult cases arise where individual elements differ, yet the overall commercial impression may still create confusion. This article examines the legal pressure points behind trademark and commercial identity disputes in the UAE, from similarity, prior use and trade names to digital infringement, domain names, interim measures, expert evidence and compensation.

Read article
The Project Is Delayed — But Who Bears the Cost? Allocating Responsibility for Delay in UAE Construction Disputes